Analisis

Priority Matrix — 7 Unit Usaha Kopdes per Fase

Unit Fase 1
2025–26
Fase 2
2027
Fase 3
2028
Fase 4
2029
Blocker Kritis
Kantor WAJIB ✓ Optimasi AI modul Self-fund SDM operator
Sembako WAJIB ✓ API Bulog Forecasting Dyn. price Internet
Simpan Pinjam WAJIB ✓ Kredit skor Fraud AI Open bank NPL monitor
Klinik Izin BPJS AKTIF Telemedicine Predictive PMK dokter
Apotek Izin BPOM AKTIF Cold chain Auto-order PMK apoteker
Logistik GPS tracker Route opt. Kolaborasi Last-mile Driver litdig
Cold Storage Bangun fisik WMS digital IoT penuh Farm-2-fork CAPEX besar
Urutan Implementasi Wajib
1st: Kantor
2nd: Sembako
3rd: Simpan Pinjam
4th: Klinik+Apotek
5th: Logistik
6th: Cold Storage
Kill Criteria — Kapan Tangguhkan Unit?
Simpan Pinjam
NPL >15% → suspend kredit baru
Klinik
Regulasi tidak selesai +6 bln → suspend
Logistik
Tidak profitable 12 bln → outsource ke swasta
Cold Storage
Okupansi <40% / 24 bln → moratorium
7 unit tidak bisa dijalankan serentak — urutan dan kill criteria ini yang membedakan program sukses vs tersebar tipis. Tanpa kriteria berhenti yang eksplisit, sumber daya habis merata di semua unit tanpa satupun yang berhasil.